st2000 pi dai si lie yuan yin fen xi ji chu li
Author(s): 
Pages: 48-49
Year: Issue:  7
Journal: Safety

Abstract: 近日,某2×600MW电厂输煤系统的C2A皮带在卸煤过程中发生一起因导料槽内部导流板脱落造成整条皮带撕裂的事件. 该厂燃煤采用海洋船舶运输方式进厂,日平均进厂煤量约9200t,整个输煤系统包括卸煤、贮煤、筛碎及上煤系统.卸煤系统起点为10万吨级卸煤码头,经过C1A、C2A、C3A三条带式输送机到达终点两座储煤量约11×104t,可供2×600MW机组燃用约22d的封闭圆形煤场.卸煤码头至圆形煤场燃煤运输采用带式输送机,带宽B=1 800mm,带速V=3.5m/s,输送能力Q=3500t/h,采用双路系统,一期工程安装一路,预留B路的位置.